The following are what an inspector looks for during a Sidewalk Inspection.
-
Concrete mix design submittal's to meet Ogden City specifications of 4,000 p.s.i. 6 ½ mix. Cold weather concrete bag mix design increases from 6 ½ bags to 7 ½ bags between October 1st to March 1st.
- Required road base depth placed and compaction test known prior to placement.
- 2% cross slope identification.
- Sidewalk concrete depth at 4 inches on either side of driveway and through driveway 6 inch depth required.
- Expansion and control joint placement.
- Broom finish.